News

India introduces paid extensions for renewable projects that miss grid milestones

India's power regulator has introduced a mechanism allowing renewable-energy developers to pay for additional time when projects miss key milestones tied to interstate grid connectivity.

Geography
Wind Turbines

The change means qualifying projects can retain their connectivity allocation for a limited period instead of automatically losing access to the transmission network when land, financing or commissioning deadlines are missed.

Developers can pay for additional time

Reuters reports that the Central Electricity Regulatory Commission will charge Rs 1,000 (£7.72) per MW per day for extensions linked to land and financing milestones, and Rs 3,000 (£23.15) per MW per day for delays in reaching commercial operation.

Projects can receive up to three additional months for land requirements, six months for financial closure and up to 12 months to commission. Developers that still miss the extended deadlines can lose their connectivity rights and associated bank guarantees.

Grid capacity cannot remain reserved indefinitely

The mechanism follows a series of cases in which renewable projects had secured transmission connectivity but were not progressing quickly enough to meet the required milestones.

CERC describes interstate grid connectivity as a scarce resource. A delayed project that continues to hold capacity can prevent another project from using the same part of the transmission system.

The new approach gives projects that are still progressing a defined route to retain their connection while creating a financial cost for holding capacity beyond the original timetable.

The same constraint appears in high-power charging

The policy is aimed at renewable generation rather than EV charging, but the underlying grid issue is familiar to large charging projects: securing network capacity early has value, and unused capacity can become a constraint for other connections.

For high-power charging hubs and fleet depots, the lesson is straightforward. Grid connection milestones, project delivery and equipment procurement need to remain aligned so that network capacity is not secured long before a site is capable of using it.

Related articles

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Necessary

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.